The Caltrans Culvert Rehabilitation project rehabilitated 13 culverts along I-8 in Alpine, California, as some of these culverts are more than 50 years old. Some culverts were lined with a cured-in-place (CIPP) liner while others were rehabilitated with concrete invert paving.

The work included the following: Full culvert cleanout, rust removal on corrugated peaks where nelson studs were welded, grouting/fill of any voids in the flow line, stud installation, wire mesh installation, shotcrete placement, and contact grout of discovered voids along walls above spring-line.

Culverts 3, 5, 8, and 11 were to be lined with steel nelson studs welded to wire mesh for reinforcement and lined with 6000-psi shotcrete. JWF self-performed the reinforcement installation and concrete invert paving, while a subcontractor placed the shotcrete.

JWF was responsible for diverting groundwater from the flowline of each culvert with an approved diversion plan. After implementing the diversion plan for the first time on Culvert 5, it was discovered that perched groundwater was still infiltrating the flowline to the point that the inspector required further measures to be taken. To remove the perched groundwater JWF installed wells 18” below flowline with additional pumps routed to the main diversion line every 50 feet. This was performed on all culverts except 8.

Each culvert only had main access from one portal where all materials and work would only be able to progress from one end. Large equipment was not allowed down to the culverts resulting in having materials delivered offsite and manually brought into each culvert.

Each culvert was different and possessed its own challenges, but all were rehabilitated in the same overall manner. Culvert 3 was the final culvert rehabilitated and was the largest (15’ diameter / 600 LF). This culvert presented many challenges including a significant settlement along the middle 200’.

Client

State of California

Region

California

Capabilities

Additional Capabiities